I love the smell of heavy industry in the morning....and the morning it was...6am to be precise. We hadn't gone to bed yet because of driving straight up from London the night before. I'm still not convinced this was not the cause of an on-going Rookinella lung problem because the dust and shit that we must have breathed in whilst exploring can't have been good. You know when your mouth feels gritty and earthen?

Anyway, it was an amazing place and so big. It reminded me of Beringen because of the tracks on the ground and the colours of the machines. It's due to be demolished any day now so I'd suggest getting your skates on if you want to see it. Cheers to Shadow for the info!

Here's the photos:

_DSC3048Re.jpg


_DSC3067Re.jpg


_DSC3098Re.jpg


_DSC3035R.jpg


_DSC3037R.jpg


_DSC3040R.jpg


_DSC3043R.jpg


_DSC3044R.jpg


_DSC3050R.jpg


_DSC3054R.jpg


_DSC3056R.jpg


_DSC3059R.jpg


_DSC3062R.jpg


_DSC3065R.jpg


_DSC3069R.jpg


_DSC3072R.jpg


_DSC3074R.jpg


_DSC3075R.jpg


_DSC3079R.jpg


_DSC3081R.jpg


_DSC3088R.jpg


_DSC3091R.jpg


_DSC3093R.jpg


_DSC3095R.jpg


_DSC3097R.jpg


_DSC3100R.jpg


_DSC3102R.jpg


_DSC3105R.jpg


_DSC3107R.jpg
 

Tony S

28DL Full Member
28DL Full Member
I'm an ex Stantonian.

I thought I'd list what the kit is that you were looking at

1. Pipe annealing stove. Pipes are heated to make the iron ductile
2. De-carburising shaking ladle frames and fume extract hoods
3. Hot blast main feeding hot air to the cupola twyres
4. Hot metal transfer bogie track, the electric furnace switch room is to the left
5. Hallam casting machine, the wet spray lance is to the left, the casting trough to the right
6. Hallam casting machine
7. Hydraulic valve manifold. That one never worked in the 12 years I was there
8. Pipe rotate guard
9. Pipe annealing stove
10. Visitors walk-way
11. Visitors walk-way, the stove is to the centre, Demag crane track to the right
12. Pipe tilters. Pipes are cast horizontally and then up-ended to go in to the stove. I re-designed the control program for these beasts
13. Inside the casting machine. The pipe mould would rotate on the rollers. I slipped and tried head-butting one of the rollers, it hurt :banghead
14. Slag pans
15. Storage point for specialised slings
16. Shaking ladle frame control and additives control panels
17. Control desk, what’s left of it
18. Shaking ladle frame control panel
19. The dreaded clocking on machine
20. Melting plant main shop
21. Hose storage racks
22. Combustion chamber gas burner control panel
23. ;)
24. Bottom of the additives bunkers
25. ;)
26. Side of the combustion chamber
27. Melting plant main shop
28. Stock ground cranes and the dispatch conveyor. These cranes picked up 8 Tonne pipes by vacuum
29. I’ll say nothing
 