real time web analytics
Report - - Chernobyl and Pripyat 08/2010 part 3. | European and International Sites | 28DaysLater.co.uk

Report - Chernobyl and Pripyat 08/2010 part 3.

Hide this ad by donating or subscribing !

O

Oldskool

Guest
Guest
In this report a little incite to what's going on in Chernobyl today and photos of the swimming pool,the school and a few shots from a roof top to show you the scale of Pripyat.....


Chernobyl today
Chernobyl unit 4 is now enclosed in a large concrete shelter which was erected quickly to allow continuing operation of the other reactors at the plant. However, the structure is neither strong nor durable. The international Shelter Implementation Plan in the 1990s involved raising money for remedial work including removal of the fuel-containing materials. Some major work on the shelter was carried out in 1998 and 1999. Some 200 tonnes of highly radioactive material remains deep within it, and this poses an environmental hazard until it is better contained.
A New Safe Confinement structure will be built by the end of 2011, and then will be moved into place on rails. It is to be an 18,000 tonne metal arch 105 metres high, 200 metres long and spanning 257 metres, to cover both unit 4 and the hastily-built 1986 structure. The Chernobyl Shelter Fund, set up in 1997, had received €810 million from international donors and projects towards this project and previous work. It and the Nuclear Safety Account, also applied to Chernobyl decommissioning, are managed by the European Bank for Reconstruction and Development (EBRD), which announced a €135 million contribution to the fund in May 2008. The total cost of the new shelter is estimated to be €1.2 billion

_DSC7401.jpg



Used fuel from units 1 to 3 is stored in each unit's cooling pond, in a small interim spent fuel storage facility pond (ISF-1), and in the reactor of unit 3.
In 1999, a contract was signed for construction of a radioactive waste management facility to store 25,000 used fuel assemblies from units 1-3 and other operational wastes, as well as material from decommissioning units 1-3 (which will be the first RBMK units decommissioned anywhere). The contract included a processing facility, able to cut the RBMK fuel assemblies and to put the material in canisters, which will be filled with inert gas and welded shut. They will then be transported to the dry storage vaults in which the fuel containers would be enclosed for up to 100 years. This facility, treating 2500 fuel assemblies per year, would be the first of its kind for RBMK fuel. However, after a significant part of the storage structures had been built, technical deficiencies in the concept emerged, and the contract was terminated in 2007. The interim spent fuel storage facility (ISF-2) is now planned to be completed by others by mid-2013.

_DSC7399.jpg



In April 2009, Nukem handed over a turnkey waste treatment centre for solid radioactive waste (ICSRM, Industrial Complex for Radwaste Management). In this, solid low- and intermediate-level wastes accumulated from the power plant operations and the decommissioning of reactor blocks 1 to 3 is conditioned. The wastes are processed in three steps. First, the solid radioactive wastes temporarily stored in bunkers is removed for treatment. In the next step, these wastes, as well as those from decommissioning reactor blocks 1-3, are processed into a form suitable for permanent safe disposal. Low- and intermediate-level wastes are separated into combustible, compactable, and non-compactable categories. These are then subject to incineration, high-force compaction, and cementation respectively. In addition, highly radioactive and long-lived solid waste is sorted out for temporary separate storage. In the third step, the conditioned solid waste materials are transferred to containers suitable for permanent safe storage.
As part of this project, at the end of 2007, Nukem handed over an Engineered Near Surface Disposal Facility for storage of short-lived radioactive waste after prior conditioning. It is 17 km away from the power plant at the Vektor complex within the 30-km zone. The storage area is designed to hold 55,000 m3 of treated waste which will be subject to radiological monitoring for 300 years, by when the radioactivity will have decayed to such an extent that monitoring is no longer required.
Another contract has been let for a Liquid Radioactive Waste Treatment Plant, to handle some 35,000 cubic metres of low- and intermediate-level liquid wastes at the site. This will need to be solidified and eventually buried along with solid wastes on site.
In January 2008, the Ukraine government announced a four-stage decommissioning plan which incorporates the above waste activities and progresses towards a cleared site.

_DSC7395.jpg


The swimming baths..

_DSC7355hdr1.jpg
_DSC7351hdr.jpg


DSC_0104.jpg


DSC_0106.jpg
DSC_0095.jpg


The school, which apart from the hospital was my favourite location and the most disturbing for want of a better word...

_DSC7383hdr1.jpg


_DSC7378hdr1.jpg


DSC_0115.jpg
DSC_0109.jpg


_DSC7394hdr1.jpg
_DSC7373hdr1.jpg


_DSC7388hdr1.jpg


_DSC7367hdr1.jpg


DSC_0119.jpg
DSC_0117.jpg


DSC_0113.jpg
DSC_0112.jpg


DSC_0126.jpg


DSC_0125.jpg
DSC_0121.jpg


The reading of 0.16 on the giger counter was only .4 higher than in Kiev
but it ran around 4.00-6.00 most areas ......at one point it reached 20.00 thats when we had to get the fook out of dodge and to another area with a lower reading....thanks for looking OLDSKOOL..
 

Who has read this thread (Total: 4) View details

Top